£7m upgrade for Torbay electricity network will benefit 40,000 homes and businesses

Transformer connected to substation infrastructure at Barton Hill Way Substation in Torquayplaceholder image
Transformer connected to substation infrastructure at Barton Hill Way Substation in Torquay | National Grid

The £7m upgrade to Torquay's electricity network, completed by NGED, will increase capacity and reliability, helping to meet growing demand in Torbay and parts of Kingskerswell.

Around 40,000 Torbay homes and businesses are set to benefit from a £7 million investment in the area's electricity network.

The National Grid Electricity Distribution (NGED) has completed the rebuild of Barton Hill Way Substation in Torquay, a bulk supply point (BSP) where electricity is transformed from higher to lower voltages for distribution to buildings.

The upgrade is designed to increase the capacity and reliability of the network, helping it meet the growing demand from residents, businesses and visitors in Torbay and parts of Kingskerswell.

Two new 60-tonne transformers, which each weigh the equivalent of around five double-decker buses, have been installed at the site. The previous transformers dated back to the 1960s and had served customers reliably for decades. NGED said they were not replaced because of any specific issues during summer tourism peaks, but as part of a long-term plan to future-proof the network and increase capacity to meet growing demand. The new transformers are expected to be quieter and require less maintenance.

The transformers were transported on low-loaders from their manufacturers in the Midlands, with the journey taking two days.

As part of the upgrade, new circuit breakers, switchgear, cabling and equipment buildings have been installed at the Barton Hill Way Substation.

The five-year project involved a team of 12 NGED staff, including design specialists, civil engineers and electrical engineers, supported by contractors.

Tom Weekes, NGED's Head of Major Projects for the South West, said: "Around 40,000 homes and businesses will be served by this vital upgrade which will boost reliability, capacity and future-proof our high voltage network.

"This is an important strategic long-term project. It will mean customers will be able to connect EV chargers, heat pumps, solar panels and battery storage more readily and it will enable local businesses to grow."

The upgrade will also enhance network resilience, reducing the risk of equipment-related interruptions.

The investment forms part of NGED's five-year plans to invest £1.4 billion in the South West's electricity network over five years to 2028, upgrading infrastructure to support growth, build resilience and move towards cleaner energy.