Dave Thomas: The high quality sea defence that will enhance our public spaces


How many times have you heard that the Council have received a large chunk of cash to deliver a project and it simply doesn’t happen? That was certainly the view on the street last year and residents wanted more.
Having been a councillor for 17 years, I have heard talk of this, that and the other and for one reason or another, when it comes to delivery – it simply doesn’t happen! I was determined when elected as Leader last year that we would deliver as much as we could in this administration.
The Strand in Torquay is underway and will be complete by Christmas, we are looking to make material starts on other projects that have been in the pipeline for years and it now looks like the Paignton and Preston Sea Defence replacement work will also be underway.
The proposed sea defences for Paignton and Preston will help protect local communities from projected coastal flooding over the next 50 years and beyond, hopefully the sight of those properties in various roads just off the seafront including Adelphi and Kernou Road being pumped out by the local Fire Brigade will be a scene committed to history. For any homeowner or business operator who has had to go through this scenario, it is something that never leaves you and your life is never quite the same again.
The new sea defences will not only create a safer environment for residents and visitors but will provide us with economic benefits both boosting our tourism trade and supporting local businesses.
The proposed scheme has been spoken about for a very long time. It finally came forward with lots of input and support from the community after the original idea, (which was to simply build a solid concrete wall on the edge of the green which would have looked hideous and would have done nothing to help lift the area) was rejected by the community and the previous administration, to their credit, opted to ‘start again’.
The remit for these improvements were to create a high-quality coastal defence and enhanced public space. We want to make sure it is fit for the future of Paignton and Preston seafronts.
It is a masterplan that was three years in the making and on Monday evening the plans were approved by the planning committee. This effectively means all of those plans that you have already seen and help to co-produce will now be able to be built out.
We have often seen that large scale plans like this application attract lots of unhappy or angry residents, who attend the planning committee and quite rightly make their views known.
However, on this occasion, the engagement with our community had been very extensive and over a prolonged period of time – I believe this played a large part in the very few number of observers that were in attendance at the planning committee this week.
What was even more unusual about this scheme was the fact that there were no registered speakers either for or against.
To be frank it felt more like the Council were dealing with a household application and not a £17m improvement scheme.
Many seaside locations across the UK have benefited from this kind of scheme, so it was about time that Paignton had its share.
However, we know these schemes are extremely expensive. We must not forget that we recently received £7m from the levelling-up fund, with the major funding, over £10m coming from the Environment Agency, (they just need to press the final ‘go’ button after the elections are concluded.)
It is anticipated that the project construction work will commence in November and the works are projected for completion in the second quarter of 2028. The exact phasing will be determined following engagement with the tendering contractors, although it is expected that some work at Paignton and Preston will take place concurrently during the course of the project.