Nearly a year on, how far has the Paignton and Preston Waterfront Scheme come


Torbay Council has confirmed that the Paignton and Preston Waterfront Scheme is now 84 per cent complete at Paignton North and 62 per cent complete at Preston seafront, with the project on course for full completion in February 2027.
As the Paignton and Preston Waterfront Scheme approaches the one-year mark since work began on September 29, 2025, Torbay Council has set out what has been achieved so far and what residents can expect over the coming months.
The multi-million-pound coastal defence and public realm project is now 84 per cent complete at Paignton North and 62 per cent complete at Preston seafront, according to the council, which has thanked residents, businesses and visitors for their patience and support over the summer as the scheme moves into its next phase.
New lighting columns have been installed at Paignton North, and parking has been reinstated in the area, offering what the council says is welcome access for visitors and support for local businesses. Safety fencing will remain in place on the green side of the Esplanade, meaning pedestrians will need to use the beach-side path. Motorists are asked to travel at no more than 5mph and stay alert to pedestrians, while cyclists using the Esplanade are asked to dismount or use Esplanade Road as an alternative.
From Monday, September 21, parking along the middle section of the Esplanade has been suspended to allow contractors to accelerate work on the southern section of the waterfront. During this phase, vehicles will be able to access Pier Approach and turn left towards Paignton North, with drivers able to park in the reinstated area before exiting via Esplanade Road at the Redcliffe Hotel end.
No vehicular traffic will be permitted along the middle or southern sections of the Esplanade, though pedestrian access will be maintained throughout. This phase of construction is expected to continue until early January 2027.
At Preston, more than three-fifths of the scheme has now been completed, and the project remains on course for full completion in February 2027. Residents can look forward to the return of the beach huts in time for Easter 2027.
The council is encouraging residents and visitors to continue supporting businesses along the waterfront during construction. Parking remains available at Paignton North and at the Victoria Centre, both offering access to the seafront, town centre, shops, cafés and restaurants, while on-street parking is also available along Preston seafront on Marine Drive.
The remaining two Bike Nights of the 2026 season will go ahead as planned, with participants able to use the north and restricted areas of the middle section of the Esplanade, exiting via Pier Approach or Paignton North.
Councillor Chris Lewis, deputy leader and cabinet member for place development and economic growth at Torbay Council, said: “We're pleased that substantial progress has been made across both Paignton and Preston, with key elements already taking shape and delivering visible improvements to the waterfront. The return of parking at Paignton North is an important milestone that will help support local businesses, and we would encourage residents and visitors to continue enjoying everything the waterfront has to offer while works progress. We would like to thank the community, businesses and visitors for their patience and understanding. The finished scheme will create an attractive, accessible and welcoming waterfront that can be enjoyed for many years to come.”